Project Renewable fuel processing plant

Project Owner... Covenant Energy  
Project name Renewable fuel processing plant  
Status planned  
Startup 2029  
Geodata
Country Canada  
State Saskatchewan  
Production
Type TRL 9 Commercial  
Technology Hydrotreatment  
Raw Material oilcrops, oils and fats  
Input 1 Canola  
Output 1 renewable diesel (HVO) (350,000 t/y )  
Additional Information
Technology Brief This renewable fuel processing plant planned to be constructed in the southeast corner of Saskatchewan is proposed to have a production capacity of 6,500 barrels a day or 300-325 million litres per year. Covenant Energy said its planned facility creates demand for 35 million bushels of canola seed to produce 325-350 thousand tonnes of feedstock annually. Covenant Energy is looking at the Estevan area ? which traditionally produces fossil fuels ? to be the home of its $500-million facility but added it?s exploring all options to make the final site selection on a railway. Updated article from 2025 states a target operation date of 2029.  
Contact Information
www.covenantenergy.ca  
Last Update: 2026-08-24 09:57:30